egan drive improvements
​​
​main street to 10th street
​

7/29/2020 Project Update

7/29/2020

 
Secon and the DOT&PF plan to replace subgrade material and pave Egan Drive from the Seadrome building to Seward Street. The work will take place in two phases, one being implemented and completed after the other. This work is anticipated to begin the morning of Thursday, July 30th, and each phase will take several days. Traffic restrictions and detours will be in place 24-hours per day.  

The following traffic revisions will be in place during the first phase of this work: 
  • Beginning Thursday, July 30th, outbound Egan Drive lanes will be closed from Shattuck Way to Main Street. Detour routes to outbound Egan Drive will be available via Franklin Street, 4th Street, Calhoun Ave, and 12th Street. Access to Main Street from Egan will be available via Franklin Street and 4th Street for all motorists. Please see graphic for more detail.   
  • Right hand turns from Main Street onto Egan will be permitted. Left hand turns from Main Street onto Egan will be permitted.  
  • Inbound Egan traffic will be limited to a single lane beginning at Willoughby Avenue.  
  • Left-hand turns from the inbound Egan lane onto Willoughby Avenue will be restricted.  
  • Pedestrian access will be maintained on one side of Egan or the other. Pedestrians should follow designated detour routes for any crosswalks affected by additional work zones. 
     
The following traffic revisions will be in place during the second phase of this work: 
  • A single outbound Egan Drive lane will be reopened from Shattuck Way to Main Street. 
  • Left hand turns from inbound Egan Drive onto Main Street will be closed. A detour route will be made available for motorists heading to Main St.  
  • Pedestrian access will be maintained on one side of Egan or the other. Pedestrians should follow designated detour routes for any crosswalks affected by additional work zones. 
  • All other traffic controls from the first phase of this work will remain in place from 10th Street to Seward Street during this time. 
    ​
This work is weather dependent. Updates will be provided as quickly as possible if delays are anticipated.    
Picture
The safety of the traveling public and our workers is our main concern.   
Please follow designated traffic revisions, posted pedestrian routes,  
and never enter a work zone.

Comments are closed.